Demand Factor means:
How much electrical load is actually used compared to the total connected load.
π Formula
Demand Factor=Total Connected LoadMaximum Demandβ
π Simple Example
Suppose in a building:
- 10 lights = 10 Γ 100 W = 1000 W
- 2 AC = 2 Γ 1500 W = 3000 W
- 1 Heater = 2000 W
π Total Connected Load = 6000 W
But not all devices run at the same time.
Maybe the maximum load used at one time = 4000 W
So,Demand Factor=60004000β=0.67
π Demand Factor = 0.67 (or 67%)
π‘ In One Line
Demand Factor = Actual maximum power used Γ· Total installed power
π’ Why Engineers Use It
Electrical engineers use demand factor to:
- Size transformers
- Design cables
- Calculate maximum load
- Design switchgear
Because all equipment will not run together.
β‘ Real Example (Apartment)
| Equipment | Connected Load |
|---|---|
| Lights | 5 kW |
| AC | 10 kW |
| Fans | 3 kW |
| Total Connected Load | 18 kW |
But maximum demand maybe only 12 kW
Demand Factor = 12 / 18 = 0.67
β
Important Point:
Demand Factor is always β€ 1
It can never be greater than 1.
Whta is Demand Load (Simple Explanation)
Demand Load means:
The actual electrical power required by equipment at a particular time.
It is the load that is really being used, not the total installed load.
π Simple Example
Suppose in a house you have:
| Equipment | Power |
|---|---|
| 5 Lights | 500 W |
| 2 Fans | 200 W |
| 1 AC | 1500 W |
| 1 Heater | 2000 W |
π Total Connected Load = 4200 W
But at a certain time only:
- Lights = 500 W
- Fans = 200 W
- AC = 1500 W
are running.
So the Demand Load = 2200 W
Because heater is OFF.
π In One Line
Demand Load = The power actually used at a specific time.
β‘ Demand Load vs Connected Load
| Type | Meaning |
|---|---|
| Connected Load | Total power of all installed equipment |
| Demand Load | Power actually used at a time |
π’ Example in Building
A building may have:
- Connected Load = 100 kW
- But normally only 60 kW is used
π Demand Load = 60 kW
π‘ Why It Is Important
Electrical engineers use Demand Load to decide:
- Transformer size
- Cable size
- Generator capacity
- Switchgear rating
β
Very Short Definition:
Demand Load = Actual electrical load used at a given time.
reat! Letβs understand the 3 very important electrical load terms used in electrical design and SLD calculations. Iβll keep it very simple. β‘
1οΈβ£ Connected Load
Connected Load means:
Total power of all electrical equipment installed.
Even if the equipment is ON or OFF, it is still counted.
Example
| Equipment | Power |
|---|---|
| Lights | 2 kW |
| Fans | 1 kW |
| AC | 5 kW |
| Heater | 2 kW |
π Connected Load = 10 kW
All equipment power added together.
2οΈβ£ Demand Load
Demand Load means:
The load actually used at a particular time.
Not all equipment runs at the same time.
Example
At a certain time only:
- Lights = 2 kW
- Fans = 1 kW
- AC = 5 kW
π Demand Load = 8 kW
Heater is OFF, so it is not counted.
3οΈβ£ Maximum Demand
Maximum Demand means:
The highest electrical load used at any time in a system.
It is the maximum power the system ever draws.
Example (During a day)
| Time | Load |
|---|---|
| Morning | 4 kW |
| Afternoon | 6 kW |
| Evening | 9 kW |
π Maximum Demand = 9 kW
Because that is the highest load used.
β‘ Simple Comparison
| Term | Meaning |
|---|---|
| Connected Load | Total installed equipment load |
| Demand Load | Load used at a specific time |
| Maximum Demand | Highest load used in the system |
π’ How Engineers Use This (SLD Design)
In electrical design:
- First calculate Connected Load
- Apply Demand Factor
- Find Maximum Demand
- Then size:
- Transformer
- Cables
- Switchgear
β Example
Connected Load = 100 kW
Demand Factor = 0.7
Maximum Demand =
100 Γ 0.7 = 70 kW
π‘ Since you are learning electrical SLD and load calculation, I can also show you a very practical step-by-step method engineers use:
Source β Transformer β Panel β Load calculation